一、概况
OVERVIEW
1. 甲方装饰物业系合法物业
Party A is the owner of the property.
2. 乙方为本市经工商行政管理机关核准登记,并可从事装潢装修的企业
Party B is approved and registered with the city industrial and commercial administrative organs as an
enterprise engaged in renovation and decoration.
3. 装饰施工地点
Construction site:
4. 建筑结构: 建筑面积 平方米,施工面积 平方米。
Construction area: total area (including stairwells and other common areas): m2, private living area: m2.
5. 装饰施工内容:住宅装饰,详见附件一<工程估价单>
Structure: residential.
6. 承包方式:详见附件一<工程估价单>
Contractor engagement method: See annex – (quotation).
7. 总价款: .00元,大写(人民币): 元整。
Total price: .00RMB; in words: 元整. Any changes in this price must be agreed by both parties in writing.
8. 工期:自 年 月 日开工,至 年 月 日前竣工,工时总计 天,不含国家法定节假日,乙方委派现场施工监理为 先生,联系方式:
Period: Start: (year) (month) (day); Completion before: (year) (month) (day); Total days (excluding national holidays): days. Party B's on site construction supervisor will be:
二、关于工程付款及结算的约定
TERMS OF PAYMENT
1. 工程款的付款方式如下
The payment schedule shall be as follows:
付 款 时 间
Timing of Payments 付 款 时 间
Date (yyyy.mm.dd) Amount (RMB)
合同签订后60%
After the contract is signed.
油漆工进场前30%
When half of the project period time has elapsed.
家具、灯具进场前5%
Furniture of lamps and lanterns, before the approach
验收合格后,五天内5%
Upon Acceptance of
the completion of the project.
增加工程项目100%
Project changes. 签订工程项目变更单100%
Date of signing for the project change.
空调工程项目100%
Air conditioning project
家具工程项目100%
Furniture engineering
三、关于材料供应的约定
AGREEMENT ON THE SUPPLY OF MATERIALS
1. 乙方提供的材料:乙方供应的材料、设备,如不符合设计、施工要求,应禁止使用。如已使用,对工程造成的损失由乙方负责。如甲方要另增加材料由甲方供应,并应符合下列规定:
Material provided by Party B: Any materials or equipment supplied by Party B which do not meet the design and construction requirements are prohibited. Any extra materials requested by Party A which were not in the original design must be paid for by Party A.
2. 甲方提供的材料:另拟补充附件<甲方提供材料、设备表>
甲方负责采购供应的材料、设备,应符合设计施工要求的合格产品,并应按时供应到现场。乙方发现甲方提供的材料、设备有质量问题或规格差异,应及时向甲方提出,甲方仍要求使用的,由此造成工程损失,责任由甲方承担。甲方供应的材料按时抵达现场后,由乙方负责保管
Material provided by Party A: (see the annex: “Table of Materials to be provided by the Owner”). If Party A acquires materials for the project, it should first check with Party B that the materials match to the design requirements, and once the materials are in the care of Party B, then Party B is responsible for the materials. If Party A requires some materials which do not fit to the design then it shall be the responsibility of Party A to pay any additional costs incurred by Party B.